L3 Reports | DC fast charging site reports, analyst-reviewed | RightSite

Numbers you
can trust.

A DC fast charging site is a heavy-capital, megawatt-scale bet. The L3 report prices that bet: utilization projected from our own databases, grid capacity screened, and every report reviewed by a person before it reaches you.

Get started
Site Qualificationretail pad · example
Marketplace Dr
Centennial, CO · parking lot · urban
In review Go analyst is reading every section ✓ analyst sign-off · delivered in 36 h
10-Yr NPV
$284,000
IRR
14.8%
Payback
4.9 yr
EV Traffic
High
Competition
Low
Site Compat
High
Demographics
High
EV Corridor
Yes
Growth
Medium
baseline verdict: before the $320K in identified funding below
The thin margin

The margin between profit and a major loss is smaller than it looks.

DC fast economics rarely fail in one big way. They leak. A rate schedule with demand charges you didn't price. A funding round that closed. A utilization ramp two points slower than hoped. Any one of them can eat the cushion; two can flip the verdict.

Every one of them is a knowable fact, and the report pins each down: the verified tariff, the grid screen, the funding search, utilization from our own data.

Guess at these, and the spreadsheet says whatever you want it to.

What moves this example's NPV
Verdict cushion · 10-yr NPV$284,000
what the site earns above the 9% hurdle
If these go the wrong way
Tariff & demand charges−$60K
Utilization · 2 pts slow−$80K
Make-ready not awarded−$90K
Funding round missed−$78K
None of these is a disaster on its own. Together they quietly erase the margin, which is why the report resolves each one instead of assuming it.
The utilization projection

A ten-year read on real numbers.

The financials run a full ten years, and they're only as good as the demand behind them. So every L3 report carries a five-year utilization projection: sessions, energy, and how busy each charger runs, built by RightSite's own engine from multiple data sources.

Cumulative discounted cash flow · 10-year hold
cumulative discounted cash flow break-even (NPV=0) · payback
-$724K -$472K -$220K $32K $284K break-even (NPV=0) NPV = 0 · payback 6.2y 0 2 4 6 8 10
10-Yr NPV
$284,000
above the 9% hurdle
Discounted payback
6.2 yr
of 10-yr hold
IRR
14.8%
vs 9% cost of capital
Example site · pre-tax project cash flows · 9% discount rate · net investment $724K
A person signs off

Every report ships with human review.

Models miss what people catch. Before a report reaches your dashboard, an analyst has read it, the utilization curve, the rate schedule, the funding list, and signed their name to it.

01Address in
You order with an address
that's all we need to start
02Engine run
Projection + full financials
utilization from our databases; rates, grid screen, funding, returns
RIGHTSITE ENGINE
03Analyst review
A person reads every section
sanity-checks the projection against the site, and signs off
HUMAN-REVIEWED
Power is the gating question

The right tariff makes the site. The wrong one breaks it.

DCFC tariffs are a maze of energy, demand, and service charges, and the published data is often wrong. So we verify the schedule that actually fits this load, demand charges included, and model the real electric bill. Then the report screens whether the local grid can carry the load, and what an upgrade might cost if not.

Where the electric bill goes · year 5 CONFIDENCE HIGH
Annual electrical cost
$86,400
Rate schedule
Commercial DCFC
matched to this load
energy 52%demand 38%service 10%
Demand charges, the line that surprises first-time DCFC builders, modeled from the utility's actual schedule, not a blended average.
Many utilities offer EV or clean-energy rates that lower this further; the report flags when to ask.
Grid capacity screen CONFIDENCE HIGH
Required load0.8 MW
Feeder headroom1.5 MW
Live utility capacity data where the utility publishes it; an engineering screen where it doesn't. If an upgrade were needed: $0–140K planning estimate; make-ready funding can offset it.
Indicative, and clearly labeled as such; only a utility service study is definitive.
The verdict, and the money that moves it

We hunt down the funding that turns a Hold into a Go.

The verdict stands on 10-year NPV against a 9% cost of capital, the same discipline as every RightSite report. Around it: the DCFC funding programs your site qualifies for, and the in-store revenue charging brings a retail host.

What the funding does here
up to $320,000
identified for this example, kept out of the baseline verdict until you apply it
Net investment · before$724,000
After funding applied$404,000
Hold Go
On a marginal site, that swing is the whole verdict.
DCFC funding & incentives · found for this example
State DCFC Program · Round 3Open
Up to $250,000 per site · public access required
Eligible
Utility Make-ReadyUtility
Up to $70,000 · covers site electrical work, incl. service upgrades
Eligible
Identified, this exampleup to $320,000
Apply any program in one click and the whole model recomputes. Funding-limited and first-come; the report says so, and keeps it out of the baseline verdict.
Know before you build.
Get started
Reports are decision-support estimates to inform a site decision · not financial advice.© 2026